Flat patrons entitled to compensation for delayed possession, lack of assured facilities: SC


New Delhi, August 24

The Supreme Court on Monday held that the flat patrons are entitled to compensation for “delayed handing over of possession” and for the failure of the developer to fulfil their guarantees with regard to facilities.

The high court docket put aside the decision of the National Consumer Disputes Redressal Commission (NCDRC) which, on July 2, 2019, had dismissed the complaints of 339 flat patrons by holding that they weren’t entitled to the compensation in extra of what was stipulated of their flat buy agreements for delayed possession and the dearth of assured facilities.

The purchasers had booked residential flats with DLF Southern Homes Pvt Ltd, now generally known as Begur OMR Homes Pvt. Ltd, in a undertaking referred to as Westend Heights at New Town, DLF, BTM Extension at Begu, Bengaluru.

The undertaking was being developed in an space admeasuring 27.5 acres and was to encompass 1980 items, unfold throughout nineteen towers every consisting of a stilt and eighteen flooring.

They had moved the NCDRC searching for compensation on account of delay in handing over possession of the flats, reimbursement of taxes and curiosity charged to the flat purchasers beneath the settlement , deficiency in offering facilities, levy of electrical energy costs by the developer and failure to assemble the membership home.

The NCDRC had held that delay within the handing over of flats to the purchasers was admitted, however the agreements had supplied compensation on the charge of Rs 5 per sq. foot of the tremendous space for each month of delay.

The NCDRC had additionally held that the flat purchasers who agreed to this stipulation within the agreements weren’t entitled to hunt any quantity as well as.

“We have come to the conclusion that the dismissal of the criticism by the NCDRC was misguided. The flat patrons are entitled to compensation for delayed handing over of possession and for the failure of the developer to fulfil the representations made to flat patrons in regard to the availability of facilities.

“The reasoning of the NCDRC on these facets suffers from a clear perversity and patent errors of law which have been noticed in the earlier part of this judgment. Allowing the appeals in part, we set aside the impugned judgment and order of the NCDRC dated July 2, 2019 dismissing the consumer complaint,” a bench of Justices D Y Chandrachud and Okay M Joseph mentioned in its 53-page judgement.

The bench mentioned the flat homeowners are entitled to the compensation in extra of the quantity stipulated of their agreements with the builders.

“Save and except for eleven appellants who entered into specific settlements with the developer and three appellants who have sold their right, title and interest under the ABA (agreement), the first and second respondents (developers) shall, as a measure of compensation, pay an amount calculated at the rate of 6 per cent simple interest per annum to each of the appellants,” it mentioned.

The compensation quantity shall be computed on the overall cash paid in the direction of the acquisition of the respective flats with impact from the date of expiry of thirty-six months from the execution of the respective flat buy agreements till the date of the supply of possession after the receipt of the occupation certificates, it mentioned.

The compensation quantity shall be along with the cash which has been paid over or credited by the developer on the charge of Rs 5 per sq. foot per 30 days on the time of the drawing of ultimate accounts, it mentioned.

The high court docket requested builders to pay the compensation inside a interval of 1 month from the date of this judgment and cautioned that failure in making cost, shall carry curiosity on the charge of 9 per cent each year till cost.

The plea was filed by Wg Cdr Arifur Rahman Khan and others in opposition to the order of the NCDRC dismissing their shopper complaints.

The purchasers had mentioned after reserving their flats, they have been knowledgeable in January 2011 that possession of the flats was anticipated to be accomplished by the center of 2012.

“This assurance was not fulfilled. By a communication dated 18 June 2013, the developers issued a revised timeline intimating all flat buyers that the delivery of possession would commence from October 2013. However, on 8 August 2013 another communication was issued stating that the real estate industry was affected by an economic slowdown which had hampered the pace of construction. The date for handing over possession was extended to June 2014…,” the judgement mentioned, noting the grievances of purchasers. PTI